By Stella Odueme
The Transmission Company of Nigeria (TCN) has provided newly constructed replacement houses to nine families displaced by the reconstruction of the Alaoji–Onitsha transmission line in Ihite Mbieri, Imo State.
The houses, delivered in partnership with the African Development Bank (AfDB), were commissioned and handed over to the beneficiaries on Thursday, November 26, 2026, under the project’s Resettlement Action Plan (RAP).
Speaking at the ceremony, TCN Managing Director and Chief Executive Officer, Engr. Sule Ahmed Abdulaziz, said the intervention reflected the company’s commitment to protecting the interests and dignity of communities affected by major infrastructure projects.
In a statement at the He disclosed that 10 families in Ihite Mbieri benefited from the resettlement programme, with nine receiving newly built houses, while the remaining family opted for financial compensation to construct its own home.
The replacement buildings comprise four three-bedroom semi-detached bungalows, four two-bedroom bungalows and one one-bedroom bungalow. They are equipped with boreholes, overhead water tanks, paved compounds, perimeter fences and gates.
Abdulaziz described the handover as a significant milestone, noting that it was the first time TCN had delivered fully completed replacement homes to project-affected persons.
He commended the beneficiaries for their patience and cooperation, acknowledging their sacrifice in surrendering their ancestral homes to enable the execution of infrastructure development intended to benefit the wider public.
On the transmission project, the TCN chief explained that the 138-kilometre Alaoji–Onitsha corridor had operated for years with an ageing and overloaded double-circuit line, creating transmission constraints and exposing the South-East electricity network to possible disturbances.
He said the reconstruction was being implemented under the Nigeria Transmission Expansion Project Phase 1 (NTEP-1), approved by the African Development Bank in November 2019.
The project involves upgrading the existing 330kV double-circuit transmission line linking the Alaoji Transmission Substation in Abia State to the Onitsha Transmission Substation in Anambra State into a 330kV quad-circuit line.
According to him, the transmission corridor passes through 12 local government areas across Abia, Imo and Anambra states.
He explained that the upgraded line would use GAP-type super thermal-resistant aluminium alloy conductors, steel-reinforced (GZTACSR), capable of carrying higher electricity loads while reducing conductor sag.