The Federal Government has commissioned a new 2x60MVA transmission substation in Billiri, Gombe State, and upgraded the Gombe Transmission Substation with a 300MVA and a 100MVA power transformer.
The projects add a total of 240MW at the 330kV level and 176MW at the 132kV level.
The Minister of Power, Joseph Tegbe, performed the commissioning on Thursday, 19th November, 2026, beginning with the new Billiri substation.
Speaking at Billiri, the Minister said the substation, with an installed capacity of 120MVA, equivalent to about 96MW, comprises two 60MVA transformers connected to the existing Gombe–Zabana–Yola transmission line.
He said the project was designed to address longstanding electricity infrastructure challenges constraining the productive potential of Billiri, Numan and adjoining communities, noting that reliable electricity is critical to unlocking their economic opportunities.
He described the investment as part of President Bola Tinubu’s administration’s commitment to strengthening critical transmission infrastructure and ensuring no community is denied opportunities for economic prosperity because of inadequate electricity supply.
According to him, improved electricity will strengthen supply within the Jos Electricity Distribution Company (Jos DisCo) franchise area, support businesses and other productive activities, attract investment and create employment.
He urged residents to protect the facility, warning that vandalism could undermine its benefits.
“These equipment you have here are your assets. They’ve been built for you and for your use. So I make a great appeal to you. You must take care of these facilities. Keep these facilities safe,” he said.
He commended the Gombe State Government for partnering with the Federal Government, saying Governor Muhammadu Inuwa Yahaya’s commitment had created an enabling environment for investment.
Gombe State Governor, Muhammadu Inuwa Yahaya, represented by the Commissioner for Energy and Mineral Resources, Sanusi Ahmed Pindiga, thanked President Tinubu for assenting to the Electricity Act 2023.
He said the Billiri substation would benefit host communities and adjoining states, and urged consumers to avoid electricity wastage.
The traditional ruler of Tangale Chiefdom and Seriki of Billiri, Alhaji Danladi Sanusi Dalandi, said improved electricity would support businesses, attract investment, create jobs and improve healthcare, education and other social services in the area.
From Billiri, the Minister proceeded to the Gombe Transmission Substation, where he commissioned the second project of the day, the upgrade of the station with an additional 300MVA, 330/132kV transformer and a new 100MVA, 132/33kV transformer.
The upgrade doubled transmission capacity at the station from 300MVA to 600MVA at the 330kV level.
The replacement of an existing 30MVA transformer with the 100MVA unit also raised downstream capacity to 220MVA, equivalent to 176MW.
The upgrade is expected to improve electricity supply to more than 70,000 additional households in Gombe and neighbouring parts of the North-East, including Yobe State.
Tegbe said the upgrade would accommodate growing demand, with benefits extending to other parts of the North-East.
In his welcome address, the Managing Director/CEO of the Transmission Company of Nigeria (TCN), Sule Ahmed Abdulaziz, said demand in Gombe and areas supplied by the station had outgrown its previous configuration.
He said TCN awarded the project in June 2021 and completed it in June 2026.
“The new transformers provide our system operators with greater operational flexibility,” he said. “At the 330kV level, the station now has increased capacity to wheel more power onward. At the 132/33kV level, the larger unit provides Jos DisCo with increased offtake capacity to serve customers in Gombe.”
Abdulaziz urged residents to protect the installations and report vandalism or suspicious activities to security agencies or the nearest TCN office.
He also urged Jos DisCo to maximise available capacity by taking more power for its customers.